This guide outlines the official steps and administrative procedures for securing a building permit in the municipality of Silang, Cavite, as posted by the Office of the Building Official (OBO).

Part 1: How to Get Your Building Permit (Applicant Steps)
According to the official OBO infographic, the application process for the public consists of the following sequential steps:
- Get application form from OBO
- See checklist of requirements depending on the type of construction
- Strict requirement: Strictly complete requirements first before submitting.
- Upon completion of requirements, submit application form on OBO
- WAIT until our staff contacts you for payment detail/amount
- Payment of assessment
- Processing/signing of Certificate of Building Permit & other Ancillary Forms
- Duration: This process takes 1–2 days.
- Releasing of permit
- WAIT until our staff contacts you for the release of building permit and tarpaulin
Part 2: The 10-Step Building Permit Process (Internal OBO Workflow)
The poster also details the internal workflow of how applications are processed by the Office of the Building Official:
- Checking of attachments for building permit
- Receiving of application for building permit
- Reviewing of plans (sanitary/plumbing, electrical, structural, architectural) & give recommendations + signing of plans
- Assessment of plans/application
- Sub-step: Inform applicant for payment.
- Payment
- Requirement: Photocopy of assessment & receipt.
- Control number of Building Permit
- Printing of template for Building Permit
- Signing of attached permits and templates
- Encoding & Filing
- Releasing
Official Contact Channels
For inquiries and updates, the Office of the Building Official of Silang, Cavite provides the following contact channels at the bottom of the poster:
- Facebook: OBO Silang Cavite
- Gmail: obosilangcavite@gmail.com